Kelso Road Bridge (Structure 74)

Completed Pending Warranty / Community Services / Infrastructure Management / Bridges/Culverts Redevelopment

Budget

$1,529,778 spent so far of the $2,538,372 originally approved (94% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $916,647 to $1,621,725 (-36%).

94% of the current budget has been drawn.

Originally approved by Council$2,538,372
Change since approval-$916,647
Current budget$1,621,725
Spent to date$1,529,778
Against the original approval$1,008,594 not yet spent — still in progress

Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$2,538,372$1,621,725$1,529,72494%
2026-06-22$2,538,372$1,621,725$1,529,72494%
2026-09-14$2,538,372$1,621,725$1,529,77894%

The figure Council approved has not changed across these statements. Spending against it rose by $54 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.