The Milton Record

Capital works

What the Town is building, where, and what it costs. Every project is measured against the budget Council originally approved; where Council later changed that budget, the change is shown alongside rather than hidden inside the comparison.

38 works on the Town’s published map, 37 of them placed in a ward. 7 carry a budget line of their own and can be measured against a figure Council approved — $36,431,353 approved and $11,762,526 spent across those 7, which is not the cost of the capital programme and is not offered as one. The other 31 are funded through program-level lines such as the Asphalt Overlay Program rather than a line per street, so there is no per-street figure to show — and none is invented here.

Aird Courtno budget line

DUNCAN LANE to DUNCAN LANE

Ward 1
Appleby Line15% drawn
C350005

Appleby Line Ph 3 - from Derry Road to south of hairpin turn; design underway with construction expected in 2026 depending on land and permits

collectorWard 16 months 2025+ 2 months 2026original $7,088,480spent $1,075,343budget raised $115,364
Chandler Crescentno budget line

FARRINGTON CROSSING to DUNCAN LANE

Ward 1
Childs Driveno budget line
C330146

2 mapped stretches: Childs Drive from ONTARIO STREET -TO- NIPISSING ROAD · Childs Drive from NIPISSING ROAD -TO- ROBERTSON CRESCENT, WEST LEG

collectorWard 22025 - 2027 Construction
Chudleigh Wayno budget line

SOUTH END to REGIONAL ROAD 4 - JAMES SNOW PARKWAY

Ward 1
Coulter Wayno budget line

BENNETT BOULEVARD to HEPBURN ROAD

Ward 3
Cousens Terraceno budget line

MADDOCKS TRAIL to MADDOCKS TRAIL

Ward 3
Campbellville Road4% drawn
C390112
culvertoriginal $870,316spent $31,487
Ellenton Crescentno budget line

2 mapped stretches: ( TO ) ELLENTON CRESCENT-TO-FERGUSON DRIVE · ( TO ) ELLENTON CRESCENT-TO-ELLENTON CRESCENT

local roadWard 3
Ezard Crescentno budget line

PETTIT TRAIL to PETTIT TRAIL

Ward 2
Fasken Courtno budget line

CUMMING BOULEVARD to FASKEN COURT

Ward 2
Fifth Lineno budget line
C340047

2026-2028, Derry to Britannia. Widening to 4 lanes and urbanization; Detailed design to start in 2022; with construction anticipated 2025;

collectorWard 32026-2028
First Line Nassagaweyano budget line

2 mapped stretches: NO 17 SIDE ROAD to 11032 FIRST LINE NASSAWAGEYA. Estimated project year is 2026 - 2027 · NO 17 SIDE ROAD to NO 20 SIDE ROAD. Estimated project year is 2026 - 2027

collectorWard 1Estimated project year is 2026 - 2027
Goutouski Crescentno budget line

GASTLE WAY to MAGURN GATE

Ward 4
Holdsworth Crescentno budget line

GLEESON ROAD to GLEESON ROAD

Ward 3
Lamont Crescentno budget line

WILLMOTT CRESCENT to WILLMOTT CRESCENT

Ward 2
Lesage Crescentno budget line

GRANT WAY to FARRINGTON CROSSING

Ward 1
Mara Circleno budget line

MEIGHEN WAY to MEIGHEN WAY

Ward 3
Marshall Crescentno budget line

( TO ) FOURTH LINE-TO-MARSHALL CRESCENT

local roadWard 3
Mccartney Crescentno budget line

LAIDLAW DRIVE to PETTIT TRAIL

Ward 2
Mcmullen Crescentno budget line

DENYES WAY to DENYES WAY

Ward 2
Mctrach Crescentno budget line

GLEAVE TERRACE to WILLET TERRACE

Ward 4
Meighen Wayno budget line

2 mapped stretches: FREEMAN TRAIL to FERGUSON DRIVE · BENNETT BOULEVARD to FREEMAN TRAIL

Ward 3
Morobel Street12% drawn
C33100225

STEELES AVE TO END

local roadWard 12026 Constructionoriginal $1,385,909spent $128,503budget reduced $328,631
Nipissing Road20% drawn
C330146

Nipissing Road from Childs Drive to Thompson; Construction began in 2025

collectorWard 22025 - 2027 Constructionoriginal $21,286,763spent $6,375,168budget raised $9,932,141
No 2 Side Roadno budget line

BELL SCHOOL LINE to TREMAINE ROAD. Estimated project year is 2026 - 2027

Ward 4Estimated project year is 2026 - 2027
Ontario Street82% drawn

3 mapped stretches: (TO) CHILDS DRIVE -TO -PINE STREET · (TO) PINE STREET -TO -MAIN STREET EAST · (TO) LAURIER AVENUE -TO -CHILDS DRIVE

local roadWard 1Ward 2original $3,885,865spent $3,768,090budget raised $737,387
Panton Trailno budget line

WELLER CROSSING to WELLER CROSSING

Ward 2
Pearl Street17% drawn
C33100325

COMMERCIAL STREET TO EAST END

local roadWard 12026 Constructionoriginal $886,674spent $106,061budget reduced $263,608
Peddie Roadno budget line

NO 5 SIDE ROAD to REGIONAL ROAD 25

Ward 1
Raftis Crescentno budget line

MAQUIRE TERRACE to MAQUIRE TERRACE

Ward 3
Sales Courtno budget line

MCJANNET to MCJANNET

Ward 4
Savoline Boulevardno budget line

2 mapped stretches: ( TO ) DYMOTT AVENUE-TO-MCJANNETT AVENUE · ( TO ) MCJANNETT AVENUE-TO-RR7 DERRY ROAD

Ward 1Ward 4
Silver Courtno budget line

MCDOUGALL CROSSING to MCDOUGALL CROSSING

Ward 4
Strathcona Courtno budget line

WEST END to CHURCHILL AVENUE

Ward 2
Switzer Crescentno budget line

PHILBROOK DRIVE to COUSENS TERRACE

Ward 3
Thompson Road26% drawn
C340020

Louis St. Laurent to Derry. Localized pathway work on west side of Thompson

arterialWard 31 YEARoriginal $1,027,346spent $277,874budget raised $54,574
Wettlaufer Terraceno budget line

PRINGLE AVENUE to JELINIK TERRACE

Ward 1

The budget tracker

The current capital financial statement carries 303 project lines with an approved budget. 29 have spent more than Council originally approved; 23 finished under. 246 are in progress and 5 not yet drawn on.

These are lines from the Town’s financial statement, not the mapped works listed above — the two are published separately and only a few can be joined with confidence, so they are not merged here.

Every budget line, with the ones furthest over and furthest under the original approval at the top →

The full lists