C390112 · culvert
$31,487 spent so far of the $870,316 originally approved (4% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
4% of the current budget has been drawn.
| Originally approved by Council | $870,316 |
|---|---|
| Change since approval | — |
| Current budget | $870,316 |
| Spent to date | $31,487 |
| Against the original approval | $838,829 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 10. Matched to this project by model at 100% confidence. This figure was read from that page, and is the Town’s published number. On spent to date, the 7 lines this site placed under that section add to $3,546,855 against $3,546,853 stated in the document, a difference of $2. A difference that small across figures printed to the dollar is what rounding looks like, so the total is not treated as verified, and the difference is stated rather than smoothed away. Document 16410, page 10.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-05-26 | $870,316 | $870,316 | — | 0% |
| 2025-06-23 | $870,316 | $870,316 | — | 0% |
| 2025-09-08 | $870,316 | $870,316 | $25,349 | 3% |
| 2025-12-08 | $870,316 | $870,316 | $25,349 | 3% |
| 2026-04-13 | $870,316 | $870,316 | $25,349 | 3% |
| 2026-05-11 | $870,316 | $870,316 | $30,235 | 3% |
| 2026-06-22 | $870,316 | $870,316 | $30,378 | 3% |
| 2026-09-14 | $870,316 | $870,316 | $31,487 | 4% |
The figure Council approved has not changed across these statements. Spending against it rose by $31,487 over the same period.
| Project manager | Mark Norman |
|---|---|
| Contact | 905-878-7252 ext. 2277 |
| Responsibility | Town of Milton |