Thompson Road

C340020 · arterial · Proposed

What it is

Louis St. Laurent to Derry. Localized pathway work on west side of Thompson

Budget

$277,874 spent so far of the $1,027,346 originally approved (26% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $54,574 to $1,081,920 (+5%).

26% of the current budget has been drawn.

Originally approved by Council$1,027,346
Change since approval$54,574
Current budget$1,081,920
Spent to date$277,874
Against the original approval$749,472 not yet spent — still in progress

Source: capital financial statement, document 16410, page 9. Matched to this project by exact-core at 97% confidence. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$526,967$539,684$73,42114%
2025-05-26$1,027,346$1,072,029$97,8279%
2025-06-23$1,027,346$1,072,029$101,0859%
2025-09-08$1,027,346$1,072,029$133,96912%
2025-12-08$1,027,346$1,072,029$244,14023%
2026-04-13$1,027,346$1,081,920$265,61025%
2026-05-11$1,027,346$1,081,920$271,35325%
2026-06-22$1,027,346$1,081,920$275,30525%
2026-09-14$1,027,346$1,081,920$277,87426%

The figure Council approved changed by $500,379 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $204,453 over the same period.

Timeline and contact

Anticipated start2026-01-01
Completion2026-12-31
Duration1 YEAR
StatusPROPOSED
Every record in the Town’s capital works layer is marked Proposed, so it says this work is in the 2026 capital programme, not that it has yet to start. $277,874 has already been drawn against it, which is the part that answers whether work has begun.
Project managerDIANA BETANCOUR
Contact905-878-7252 ext 2398
ResponsibilityTown of Milton

What has changed

2026-09-28
No longer in the capital works program: THOMPSON ROAD (C340020) — usually means it finished or moved to a later year.
2026-09-28
New capital works project: THOMPSON ROAD (C340020) — arterial, status PROPOSED. Scheduled 2026-01-01 to 2026-12-31.
2026-09-27
No longer in the capital works program: THOMPSON ROAD (C340020) — usually means it finished or moved to a later year.
2026-09-27
New capital works project: THOMPSON ROAD (C340020) — arterial, status PROPOSED. Scheduled 2026-01-01 to 2026-12-31.
2026-08-23
New capital works project: THOMPSON ROAD (C340020) — arterial, status PROPOSED. Scheduled 2026-01-01 to 2026-12-31.

Nearby capital works, by name

Elsewhere on this site