11 days until Milton votes. Monday 26 October 2026. Everyone on the ballot, what each has filed, and what they say in their own words — see the ballot.
C340020 · arterial · Proposed
$277,874 spent so far of the $1,027,346 originally approved (26% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $54,574 to $1,081,920 (+5%).
26% of the current budget has been drawn.
| Originally approved by Council | $1,027,346 |
|---|---|
| Change since approval | $54,574 |
| Current budget | $1,081,920 |
| Spent to date | $277,874 |
| Against the original approval | $749,472 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 9. Matched to this project by exact-core at 97% confidence. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $526,967 | $539,684 | $73,421 | 14% |
| 2025-05-26 | $1,027,346 | $1,072,029 | $97,827 | 9% |
| 2025-06-23 | $1,027,346 | $1,072,029 | $101,085 | 9% |
| 2025-09-08 | $1,027,346 | $1,072,029 | $133,969 | 12% |
| 2025-12-08 | $1,027,346 | $1,072,029 | $244,140 | 23% |
| 2026-04-13 | $1,027,346 | $1,081,920 | $265,610 | 25% |
| 2026-05-11 | $1,027,346 | $1,081,920 | $271,353 | 25% |
| 2026-06-22 | $1,027,346 | $1,081,920 | $275,305 | 25% |
| 2026-09-14 | $1,027,346 | $1,081,920 | $277,874 | 26% |
The figure Council approved changed by $500,379 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $204,453 over the same period.
| Anticipated start | 2026-01-01 |
|---|---|
| Completion | 2026-12-31 |
| Duration | 1 YEAR |
| Status | PROPOSED Every record in the Town’s capital works layer is marked Proposed, so it says this work is in the 2026 capital programme, not that it has yet to start. $277,874 has already been drawn against it, which is the part that answers whether work has begun. |
| Project manager | DIANA BETANCOUR |
| Contact | 905-878-7252 ext 2398 |
| Responsibility | Town of Milton |