The Milton Record

Appleby Line

C350005 · collector · Proposed

What it is

Appleby Line Ph 3 - from Derry Road to south of hairpin turn; design underway with construction expected in 2026 depending on land and permits

Budget

$1,075,343 spent so far of the $7,088,480 originally approved (15% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $115,364 to $7,203,844 (+2%).

15% of the current budget has been drawn.

Originally approved by Council$7,088,480
Change since approval$115,364
Current budget$7,203,844
Spent to date$1,075,343
Against the original approval$6,013,137 not yet spent — still in progress

Source: capital financial statement, document 16410, page 10. Matched to this project by exact-core at 97% confidence. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$2,602,136$4,421,356$3,835,44487%
2025-05-26$8,986,448$10,805,668$3,934,81836%
2025-06-23$8,986,448$10,805,668$3,942,56536%
2025-09-08$8,986,448$10,805,668$4,145,64738%
2025-12-08$8,986,448$10,805,668$4,214,79439%
2026-04-13$7,088,480$7,284,424$874,39912%
2026-05-11$7,088,480$7,331,027$927,19413%
2026-06-22$7,088,480$7,203,844$965,68713%
2026-09-14$7,088,480$7,203,844$1,075,34315%

The figure Council approved changed by $4,486,344 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.

Timeline and contact

Duration6 months 2025+ 2 months 2026
StatusPROPOSED
Every record in the Town’s capital works layer is marked Proposed, so it says this work is in the 2026 capital programme, not that it has yet to start. $1,075,343 has already been drawn against it, which is the part that answers whether work has begun.
Project managerDIANA BETANCOUR
Contact905-878-7252 ext 2398
ResponsibilityTown of Milton

What has changed

2026-09-28
No longer in the capital works program: APPLEBY LINE (C350005) — usually means it finished or moved to a later year.
2026-09-28
New capital works project: APPLEBY LINE (C350005) — collector, status PROPOSED.
2026-09-27
No longer in the capital works program: APPLEBY LINE (C350005) — usually means it finished or moved to a later year.
2026-09-27
New capital works project: APPLEBY LINE (C350005) — collector, status PROPOSED.
2026-08-23
New capital works project: APPLEBY LINE (C350005) — collector, status PROPOSED.

Other collector projects

Elsewhere on this site