Nipissing Road

C330146 · collector · Proposed

What it is

Nipissing Road from Childs Drive to Thompson; Construction began in 2025

Budget

$6,375,168 spent so far of the $21,286,763 originally approved (20% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $9,932,141 to $31,218,904 (+47%).

20% of the current budget has been drawn.

Originally approved by Council$21,286,763
Change since approval$9,932,141
Current budget$31,218,904
Spent to date$6,375,168
Against the original approval$14,911,595 not yet spent — still in progress

Source: capital financial statement, document 16410, page 9. Matched to this project by exact-core at 97% confidence. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$3,314,698$2,767,273$780,68828%
2025-05-26$21,286,763$20,739,338$981,5435%
2025-06-23$21,286,763$20,739,338$1,026,0235%
2025-09-08$21,286,763$31,218,904$1,570,9245%
2025-12-08$21,286,763$31,218,904$2,321,2827%
2026-04-13$21,286,763$31,218,904$3,043,67610%
2026-05-11$21,286,763$31,218,904$3,966,46213%
2026-06-22$21,286,763$31,218,904$4,963,87516%
2026-09-14$21,286,763$31,218,904$6,375,16820%

The figure Council approved changed by $17,972,065 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $5,594,480 over the same period.

Timeline and contact

Anticipated start2025-07-15
Completion2027-07-31
Duration2025 - 2027 Construction
StatusPROPOSED
Every record in the Town’s capital works layer is marked Proposed, so it says this work is in the 2026 capital programme, not that it has yet to start. $6,375,168 has already been drawn against it, which is the part that answers whether work has begun.
Project managerDavid Muraca
Contact905-878-7252 ext 2398
ResponsibilityTown of Milton

What has changed

2026-09-28
No longer in the capital works program: NIPISSING ROAD (C330146) — usually means it finished or moved to a later year.
2026-09-28
No longer in the capital works program: CHILDS DRIVE (C330146) — usually means it finished or moved to a later year.
2026-09-28
New capital works project: CHILDS DRIVE (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-09-28
New capital works project: NIPISSING ROAD (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-09-27
No longer in the capital works program: CHILDS DRIVE (C330146) — usually means it finished or moved to a later year.
2026-09-27
No longer in the capital works program: NIPISSING ROAD (C330146) — usually means it finished or moved to a later year.
2026-09-27
New capital works project: NIPISSING ROAD (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-09-27
New capital works project: CHILDS DRIVE (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-08-23
New capital works project: CHILDS DRIVE (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-08-23
New capital works project: CHILDS DRIVE (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.
2026-08-23
New capital works project: NIPISSING ROAD (C330146) — collector, status PROPOSED. Scheduled 2025-07-15 to 2027-07-31.