Pearl Street

C33100325 · local road · Proposed

What it is

COMMERCIAL STREET TO EAST END

Budget

$106,061 spent so far of the $886,674 originally approved (17% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $263,608 to $623,066 (-30%).

17% of the current budget has been drawn.

Originally approved by Council$886,674
Change since approval-$263,608
Current budget$623,066
Spent to date$106,061
Against the original approval$780,613 not yet spent — still in progress

Source: capital financial statement, document 16410, page 9. Matched to this project by exact-core at 97% confidence. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (8 statements)

Statement dateApprovedCurrent budgetSpent%
2025-05-26$205,743$205,743$4,4972%
2025-06-23$205,743$205,743$6,1633%
2025-09-08$205,743$157,903$17,22911%
2025-12-08$205,743$157,903$27,65818%
2026-04-13$205,743$157,903$65,32441%
2026-05-11$886,674$838,834$77,9079%
2026-06-22$886,674$623,066$79,04413%
2026-09-14$886,674$623,066$106,06117%

The figure Council approved changed by $680,931 between 2025-05-26 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $101,564 over the same period.

Timeline and contact

Anticipated start2026-05-01
Completion2026-11-30
Duration2026 Construction
StatusPROPOSED
Every record in the Town’s capital works layer is marked Proposed, so it says this work is in the 2026 capital programme, not that it has yet to start. $106,061 has already been drawn against it, which is the part that answers whether work has begun.
Project managerSHAWN CLEWLOW
Contact905-878-7252 ext 2520
ResponsibilityTown of Milton

What has changed

2026-09-28
No longer in the capital works program: PEARL STREET (C33100325) — usually means it finished or moved to a later year.
2026-09-28
New capital works project: PEARL STREET (C33100325) — local road, status PROPOSED. Scheduled 2026-05-01 to 2026-11-30.
2026-09-27
No longer in the capital works program: PEARL STREET (C33100325) — usually means it finished or moved to a later year.
2026-09-27
New capital works project: PEARL STREET (C33100325) — local road, status PROPOSED. Scheduled 2026-05-01 to 2026-11-30.
2026-08-23
New capital works project: PEARL STREET (C33100325) — local road, status PROPOSED. Scheduled 2026-05-01 to 2026-11-30.

Other local road projects

Elsewhere on this site