11 days until Milton votes. Monday 26 October 2026. Everyone on the ballot, what each has filed, and what they say in their own words — see the ballot.
Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Growth
Spent $18,840,370 against an original approval of $18,333,704 — $506,666 over (+3%).
Council later raised the budget by $717,155 to $19,050,859 (+4%).
99% of the current budget has been drawn.
| Originally approved by Council | $18,333,704 |
|---|---|
| Change since approval | $717,155 |
| Current budget | $19,050,859 |
| Spent to date | $18,840,370 |
| Against the original approval | $506,666 over |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $18,333,704 | $19,050,859 | $18,839,130 | 99% |
| 2026-06-22 | $18,333,704 | $19,050,859 | $18,839,130 | 99% |
| 2026-09-14 | $18,333,704 | $19,050,859 | $18,840,370 | 99% |
The figure Council approved has not changed across these statements. Spending against it rose by $1,240 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Growth.