Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Growth
Spent $25,023,921 against an original approval of $23,501,907 — $1,522,014 over (+6%).
Council later raised the budget by $1,791,323 to $25,293,230 (+8%).
99% of the current budget has been drawn.
| Originally approved by Council | $23,501,907 |
|---|---|
| Change since approval | $1,791,323 |
| Current budget | $25,293,230 |
| Spent to date | $25,023,921 |
| Against the original approval | $1,522,014 over |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-04-28 | $23,501,907 | $26,890,345 | $25,017,118 | 93% |
| 2026-05-11 | $23,501,907 | $25,293,230 | $25,023,921 | 99% |
| 2026-06-22 | $23,501,907 | $25,293,230 | $25,023,921 | 99% |
| 2026-09-14 | $23,501,907 | $25,293,230 | $25,023,921 | 99% |
The figure Council approved has not changed across these statements. Spending against it rose by $6,803 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Growth.