Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment
Finished at $2,372,736 against an original approval of $3,220,463 — $847,727 under.
Council later reduced the budget by $821,401 to $2,399,062 (-26%).
99% of the current budget has been drawn.
| Originally approved by Council | $3,220,463 |
|---|---|
| Change since approval | -$821,401 |
| Current budget | $2,399,062 |
| Spent to date | $2,372,736 |
| Against the original approval | $847,727 under |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $3,220,463 | $2,399,062 | $2,371,675 | 99% |
| 2026-06-22 | $3,220,463 | $2,399,062 | $2,371,903 | 99% |
| 2026-09-14 | $3,220,463 | $2,399,062 | $2,372,736 | 99% |
The figure Council approved has not changed across these statements. Spending against it rose by $1,061 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment.