Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment
Finished at $4,943,879 against an original approval of $6,692,416 — $1,748,537 under.
Council later reduced the budget by $1,585,286 to $5,107,130 (-24%).
97% of the current budget has been drawn.
| Originally approved by Council | $6,692,416 |
|---|---|
| Change since approval | -$1,585,286 |
| Current budget | $5,107,130 |
| Spent to date | $4,943,879 |
| Against the original approval | $1,748,537 under |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-09-09 | $9,828,147 | $9,045,220 | $8,929,972 | 99% |
| 2024-10-07 | $9,828,147 | $9,045,220 | $8,931,470 | 99% |
| 2024-12-09 | $9,828,147 | $9,045,220 | $8,950,718 | 99% |
| 2025-04-28 | $9,828,147 | $9,045,220 | $8,953,455 | 99% |
| 2025-05-26 | $9,828,147 | $9,045,220 | $8,954,013 | 99% |
| 2025-06-23 | $9,828,147 | $9,045,220 | $8,954,013 | 99% |
| 2026-05-11 | $6,692,416 | $5,107,130 | $4,943,699 | 97% |
| 2026-06-22 | $6,692,416 | $5,107,130 | $4,943,699 | 97% |
| 2026-09-14 | $6,692,416 | $5,107,130 | $4,943,879 | 97% |
The figure Council approved changed by $3,135,731 between 2024-09-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment.