Completed Pending Warranty / Community Services / Infrastructure Management / Storm Water Management Rehabilitation
Spent $717,635 against an original approval of $576,987 — $140,648 over (+24%).
Council later raised the budget by $206,812 to $783,799 (+36%).
92% of the current budget has been drawn.
| Originally approved by Council | $576,987 |
|---|---|
| Change since approval | $206,812 |
| Current budget | $783,799 |
| Spent to date | $717,635 |
| Against the original approval | $140,648 over |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $576,987 | $783,799 | $701,127 | 89% |
| 2026-06-22 | $576,987 | $783,799 | $708,200 | 90% |
| 2026-09-14 | $576,987 | $783,799 | $717,635 | 92% |
The figure Council approved has not changed across these statements. Spending against it rose by $16,508 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.