The Milton Record

Sam Sherratt Trail Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

$8,376 spent so far of the $68,699 originally approved (12% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

12% of the current budget has been drawn.

Originally approved by Council$68,699
Change since approval
Current budget$68,699
Spent to date$8,376
Against the original approval$60,323 not yet spent — still in progress

Source: capital financial statement, document 15221, page 6. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (11 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$56,045$139,093$137,59799%
2023-03-27$56,045$139,093$137,86299%
2023-05-08$56,045$139,093$137,86299%
2023-06-19$56,045$139,093$137,86299%
2023-09-11$56,045$139,093$137,94199%
2023-09-11$56,045$139,093$137,94199%
2023-10-23$56,045$139,093$137,94199%
2023-12-18$56,045$139,093$137,94199%
2024-04-15$56,045$137,941$137,941100%
2026-05-11$68,699$68,699$6,0909%
2026-06-22$68,699$68,699$8,37612%

The figure Council approved changed by $12,654 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Parks Redevelopment

Filed by the Town under Community Services / Active / Community Services / Parks / Parks Redevelopment.

Elsewhere on this site