Omagh Park Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

Finished at $862,046 against an original approval of $905,367$43,321 under.

Council later reduced the budget by $830 to $904,537 (-0%).

95% of the current budget has been drawn.

Originally approved by Council$905,367
Change since approval-$830
Current budget$904,537
Spent to date$862,046
Against the original approval$43,321 under

Source: capital financial statement, document 15221, page 6. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (22 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$905,367$905,025$847,07594%
2023-03-27$905,367$904,537$859,67695%
2023-05-08$905,367$904,537$860,22795%
2023-06-19$905,367$904,537$860,35395%
2023-09-11$905,367$904,537$860,70495%
2023-09-11$905,367$904,537$860,70495%
2023-10-23$905,367$904,537$860,70495%
2023-12-18$905,367$904,537$860,70495%
2024-04-15$905,367$904,537$860,88395%
2024-05-13$905,367$904,537$860,88395%
2024-06-03$905,367$904,537$860,88395%
2024-09-09$905,367$904,537$860,88395%
2024-10-07$905,367$904,537$860,92895%
2024-12-09$905,367$904,537$860,92895%
2025-04-28$905,367$904,537$861,08695%
2025-05-26$905,367$904,537$861,08695%
2025-06-23$905,367$904,537$861,36595%
2025-09-08$905,367$904,537$861,55795%
2025-12-08$905,367$904,537$861,98895%
2026-04-13$905,367$904,537$862,04695%
2026-05-11$905,367$904,537$862,04695%
2026-06-22$905,367$904,537$862,04695%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.