Watson Park Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

Finished at $510,955 against an original approval of $517,958$7,003 under.

Council later reduced the budget by $2,385 to $515,573 (-0%).

99% of the current budget has been drawn.

Originally approved by Council$517,958
Change since approval-$2,385
Current budget$515,573
Spent to date$510,955
Against the original approval$7,003 under

Source: capital financial statement, document 15221, page 6. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (14 statements)
Statement dateApprovedCurrent budgetSpent%
2024-05-13$66,295$66,057$4,3527%
2024-06-03$66,295$66,057$5,6279%
2024-09-09$66,295$66,057$25,06938%
2024-10-07$66,295$66,057$30,50446%
2024-12-09$66,295$66,057$49,67275%
2025-04-28$66,295$83,069$73,15888%
2025-05-26$584,253$598,642$86,43614%
2025-06-23$584,253$598,642$91,33915%
2025-09-08$517,958$515,573$27,5955%
2025-09-08$66,295$89,903$89,903100%
2025-12-08$517,958$515,573$382,96774%
2026-04-13$517,958$515,573$507,68498%
2026-05-11$517,958$515,573$510,30499%
2026-06-22$517,958$515,573$510,95599%

The figure Council approved changed by $451,663 between 2024-05-13 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.