Pearl Street (Commercial to End)

Infrastructure Management / Urban Roads Redevelopment

Budget

$79,044 spent so far of the $886,674 originally approved (13% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $263,608 to $623,066 (-30%).

13% of the current budget has been drawn.

Originally approved by Council$886,674
Change since approval-$263,608
Current budget$623,066
Spent to date$79,044
Against the original approval$807,630 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (7 statements)
Statement dateApprovedCurrent budgetSpent%
2025-05-26$205,743$205,743$4,4972%
2025-06-23$205,743$205,743$6,1633%
2025-09-08$205,743$157,903$17,22911%
2025-12-08$205,743$157,903$27,65818%
2026-04-13$205,743$157,903$65,32441%
2026-05-11$886,674$838,834$77,9079%
2026-06-22$886,674$623,066$79,04413%

The figure Council approved changed by $680,931 between 2025-05-26 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
Pearl Street13% drawn
C33100325
Proposedlocal road2026 Constructionoriginal $886,674budget reduced $263,608