Crack Sealing Program

Infrastructure Management / Urban Roads Redevelopment

Budget

$299,724 spent so far of the $600,434 originally approved (65% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $136,067 to $464,367 (-23%).

65% of the current budget has been drawn.

Originally approved by Council$600,434
Change since approval-$136,067
Current budget$464,367
Spent to date$299,724
Against the original approval$300,710 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (14 statements)
Statement dateApprovedCurrent budgetSpent%
2024-05-13$458,695$458,695$2,4631%
2024-06-03$458,695$458,695$2,6001%
2024-09-09$33,240$33,240$4,78914%
2024-09-09$425,455-$413,063$12,39212392%
2024-10-07$33,240$33,240$5,90718%
2024-12-09$33,240$33,240$5,97718%
2025-04-28$33,240$43,383$33,34377%
2025-05-26$554,750$564,893$41,6607%
2025-06-23$554,750$564,893$42,1487%
2025-09-08$554,750$418,683$62,98415%
2025-12-08$554,750$418,683$277,53666%
2026-04-13$554,750$418,683$298,08071%
2026-05-11$600,434$464,367$299,72465%
2026-06-22$600,434$464,367$299,72465%

The figure Council approved changed by $141,739 between 2024-05-13 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Urban Roads Redevelopment

Filed by the Town under Infrastructure Management / Urban Roads Redevelopment.

Elsewhere on this site