Morobel Drive (Steeles Ave to North End)

Infrastructure Management / Urban Roads Redevelopment

Budget

$81,887 spent so far of the $1,385,909 originally approved (8% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $328,631 to $1,057,278 (-24%).

8% of the current budget has been drawn.

Originally approved by Council$1,385,909
Change since approval-$328,631
Current budget$1,057,278
Spent to date$81,887
Against the original approval$1,304,022 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (7 statements)
Statement dateApprovedCurrent budgetSpent%
2025-05-26$205,743$205,743$4,4972%
2025-06-23$205,743$205,743$6,1633%
2025-09-08$205,743$157,903$17,22911%
2025-12-08$205,743$157,903$65,34441%
2026-04-13$205,743$157,903$74,38347%
2026-05-11$1,385,909$1,338,069$80,7506%
2026-06-22$1,385,909$1,057,278$81,8878%

The figure Council approved changed by $1,180,166 between 2025-05-26 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
Morobel Street8% drawn
C33100225
Proposedlocal road2026 Constructionoriginal $1,385,909budget reduced $328,631

Other lines under Urban Roads Redevelopment

Filed by the Town under Infrastructure Management / Urban Roads Redevelopment.