Community Services / Active / Infrastructure Management / Urban Roads Redevelopment
$6,375,168 spent so far of the $21,286,763 originally approved (20% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $9,932,141 to $31,218,904 (+47%).
20% of the current budget has been drawn.
| Originally approved by Council | $21,286,763 |
|---|---|
| Change since approval | $9,932,141 |
| Current budget | $31,218,904 |
| Spent to date | $6,375,168 |
| Against the original approval | $14,911,595 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 9. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $3,314,698 | $2,767,273 | $780,688 | 28% |
| 2025-05-26 | $21,286,763 | $20,739,338 | $981,543 | 5% |
| 2025-06-23 | $21,286,763 | $20,739,338 | $1,026,023 | 5% |
| 2025-09-08 | $21,286,763 | $31,218,904 | $1,570,924 | 5% |
| 2025-12-08 | $21,286,763 | $31,218,904 | $2,321,282 | 7% |
| 2026-04-13 | $21,286,763 | $31,218,904 | $3,043,676 | 10% |
| 2026-05-11 | $21,286,763 | $31,218,904 | $3,966,462 | 13% |
| 2026-06-22 | $21,286,763 | $31,218,904 | $4,963,875 | 16% |
| 2026-09-14 | $21,286,763 | $31,218,904 | $6,375,168 | 20% |
The figure Council approved changed by $17,972,065 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $5,594,480 over the same period.
Nipissing Road from Childs Drive to Thompson; Construction began in 2025
Filed by the Town under Community Services / Active / Infrastructure Management / Urban Roads Redevelopment.