Community Services / Active / Infrastructure Management / Urban Roads Redevelopment
$7,520,819 spent so far of the $20,786,413 originally approved (52% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later reduced the budget by $6,319,699 to $14,466,714 (-30%).
52% of the current budget has been drawn.
| Originally approved by Council | $20,786,413 |
|---|---|
| Change since approval | -$6,319,699 |
| Current budget | $14,466,714 |
| Spent to date | $7,520,819 |
| Against the original approval | $13,265,594 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 9. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $25,875,355 | $24,906,083 | $22,058,168 | 89% |
| 2025-05-26 | $37,268,209 | $35,105,456 | $22,442,832 | 64% |
| 2025-06-23 | $37,268,209 | $32,139,085 | $22,447,367 | 70% |
| 2025-09-08 | $36,663,535 | $31,639,096 | $22,526,215 | 71% |
| 2025-12-08 | $36,663,535 | $31,639,096 | $27,198,032 | 86% |
| 2026-04-13 | $18,748,096 | $14,066,115 | $12,017,932 | 85% |
| 2026-05-11 | $20,786,413 | $17,635,028 | $7,162,428 | 41% |
| 2026-06-22 | $20,786,413 | $14,466,714 | $7,173,152 | 50% |
| 2026-09-14 | $20,786,413 | $14,466,714 | $7,520,819 | 52% |
The figure Council approved changed by $5,088,942 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Infrastructure Management / Urban Roads Redevelopment.