Corporate Services / Active / Corporate Services / Information Technology
$1,500 spent so far of the $51,500 originally approved (2% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $15,699 to $67,199 (+30%).
2% of the current budget has been drawn.
| Originally approved by Council | $51,500 |
|---|---|
| Change since approval | $15,699 |
| Current budget | $67,199 |
| Spent to date | $1,500 |
| Against the original approval | $50,000 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 3. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2023-05-08 | $51,500 | $51,500 | — | 0% |
| 2024-12-09 | $51,500 | $51,500 | $25,135 | 49% |
| 2025-05-26 | $103,000 | $103,000 | $25,135 | 24% |
| 2025-06-23 | $103,000 | $103,000 | $25,135 | 24% |
| 2025-09-08 | $103,000 | $103,000 | $28,851 | 28% |
| 2025-12-08 | $103,000 | $103,000 | $28,851 | 28% |
| 2026-04-13 | $103,000 | $103,000 | $37,301 | 36% |
| 2026-05-11 | $103,000 | $103,000 | $37,301 | 36% |
| 2026-06-22 | $103,000 | $103,000 | $37,301 | 36% |
| 2026-09-14 | $51,500 | $67,199 | $1,500 | 2% |
The figure Council approved has not changed across these statements. Spending against it rose by $1,500 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Information Technology.