Technology Infrastructure Initiative

Corporate Services / Active / Corporate Services / Information Technology

Budget

$31,231 spent so far of the $664,746 originally approved (1% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $1,431,725 to $2,096,471 (+215%).

1% of the current budget has been drawn.

Originally approved by Council$664,746
Change since approval$1,431,725
Current budget$2,096,471
Spent to date$31,231
Against the original approval$633,515 not yet spent — still in progress

Source: capital financial statement, document 16410, page 3. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (11 statements)

Statement dateApprovedCurrent budgetSpent%
2022-12-19$2,940,664$3,011,257$1,754,39558%
2023-05-08$2,996,088$3,066,681$1,669,98354%
2024-12-09$2,843,383$2,843,383$625,22022%
2025-05-26$3,228,811$3,228,811$625,22019%
2025-06-23$3,228,811$3,228,811$625,22019%
2025-09-08$2,168,105$2,168,105$330,32015%
2025-12-08$2,168,105$2,168,105$371,08117%
2026-04-13$878,048$1,884,691$87,6675%
2026-05-11$1,165,468$2,172,111$87,6674%
2026-06-22$1,165,468$2,172,111$87,6674%
2026-09-14$664,746$2,096,471$31,2311%

The figure Council approved changed by $2,275,918 between 2022-12-19 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Information Technology

Filed by the Town under Corporate Services / Active / Corporate Services / Information Technology.

Elsewhere on this site