The Milton Record

Property Tax System Replacement

Corporate Services / Active / Corporate Services / Information Technology

Budget

$1,384,493 spent so far of the $3,152,242 originally approved (59% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $808,622 to $2,343,620 (-26%).

59% of the current budget has been drawn.

Originally approved by Council$3,152,242
Change since approval-$808,622
Current budget$2,343,620
Spent to date$1,384,493
Against the original approval$1,767,749 not yet spent — still in progress

Source: capital financial statement, document 16410, page 3. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (11 statements)

Statement dateApprovedCurrent budgetSpent%
2022-12-19$1,895,180$164,088$64,08839%
2023-05-08$2,124,324$393,232$64,08816%
2024-12-09$3,381,386$2,350,294$610,36226%
2025-05-26$3,381,386$2,350,294$610,36226%
2025-06-23$3,381,386$2,350,294$640,89027%
2025-09-08$3,381,386$2,350,294$726,45831%
2025-12-08$3,381,386$2,350,294$860,05137%
2026-04-13$3,152,242$2,343,620$930,28840%
2026-05-11$3,152,242$2,343,620$1,053,81245%
2026-06-22$3,152,242$2,343,620$930,28840%
2026-09-14$3,152,242$2,343,620$1,384,49359%

The figure Council approved changed by $1,257,062 between 2022-12-19 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $1,320,405 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Information Technology

Filed by the Town under Corporate Services / Active / Corporate Services / Information Technology.

Elsewhere on this site