11 days until Milton votes. Monday 26 October 2026. Everyone on the ballot, what each has filed, and what they say in their own words — see the ballot.
Corporate Services / Active / Corporate Services / Information Technology
$67,583 spent so far of the $432,111 originally approved (13% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $68,699 to $500,810 (+16%).
13% of the current budget has been drawn.
| Originally approved by Council | $432,111 |
|---|---|
| Change since approval | $68,699 |
| Current budget | $500,810 |
| Spent to date | $67,583 |
| Against the original approval | $364,528 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 3. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2023-05-08 | $294,812 | $294,812 | — | 0% |
| 2024-12-09 | $432,111 | $500,810 | $53,356 | 11% |
| 2025-05-26 | $432,111 | $500,810 | $62,427 | 12% |
| 2025-06-23 | $432,111 | $500,810 | $64,112 | 13% |
| 2025-09-08 | $432,111 | $500,810 | $67,439 | 13% |
| 2025-12-08 | $432,111 | $500,810 | $67,583 | 13% |
| 2026-04-13 | $432,111 | $500,810 | $67,583 | 13% |
| 2026-05-11 | $432,111 | $500,810 | $67,583 | 13% |
| 2026-06-22 | $432,111 | $500,810 | $67,583 | 13% |
| 2026-09-14 | $432,111 | $500,810 | $67,583 | 13% |
The figure Council approved changed by $137,299 between 2023-05-08 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $67,583 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Information Technology.