Development Services / Active / Planning and Development / Planning
$13,215 spent so far of the $323,420 originally approved (4% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
4% of the current budget has been drawn.
| Originally approved by Council | $323,420 |
|---|---|
| Change since approval | — |
| Current budget | $323,420 |
| Spent to date | $13,215 |
| Against the original approval | $310,205 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 12. These figures were parsed from that document and reconciled against the totals it states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-05-13 | $323,420 | $323,420 | $98 | 0% |
| 2024-06-03 | $323,420 | $323,420 | $98 | 0% |
| 2024-09-09 | $323,420 | $323,420 | $11,206 | 3% |
| 2024-10-07 | $323,420 | $323,420 | $11,484 | 4% |
| 2024-12-09 | $323,420 | $323,420 | $11,484 | 4% |
| 2025-04-28 | $323,420 | $323,420 | $11,484 | 4% |
| 2025-05-26 | $323,420 | $323,420 | $11,484 | 4% |
| 2025-06-23 | $323,420 | $323,420 | $11,484 | 4% |
| 2025-09-08 | $323,420 | $323,420 | $11,484 | 4% |
| 2025-12-08 | $323,420 | $323,420 | $11,484 | 4% |
| 2026-04-13 | $323,420 | $323,420 | $12,203 | 4% |
| 2026-05-11 | $323,420 | $323,420 | $13,215 | 4% |
| 2026-06-22 | $323,420 | $323,420 | $13,215 | 4% |
The figure Council approved has not changed across these statements.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Development Services / Active / Planning and Development / Planning.