Britannia E/W - Secondary Plan

Development Services / Active / Planning and Development / Planning

Budget

Spent $2,683,991 against an original approval of $2,389,887$294,104 over (+12%).

Council later raised the budget by $1,257,251 to $3,647,138 (+53%).

74% of the current budget has been drawn.

Originally approved by Council$2,389,887
Change since approval$1,257,251
Current budget$3,647,138
Spent to date$2,683,991
Against the original approval$294,104 over

Source: capital financial statement, document 15221, page 12. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (22 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$2,389,887$3,255,455$1,553,52448%
2023-03-27$2,389,887$3,255,455$1,600,12249%
2023-05-08$2,389,887$3,255,455$1,618,10550%
2023-06-19$2,389,887$3,255,455$1,770,27654%
2023-09-11$2,389,887$3,255,455$1,813,58956%
2023-09-11$2,389,887$3,255,455$1,813,58956%
2023-10-23$2,389,887$3,255,455$1,816,04656%
2023-12-18$2,389,887$3,647,138$1,823,88450%
2024-04-15$2,389,887$3,647,138$1,858,92951%
2024-05-13$2,389,887$3,647,138$1,911,65152%
2024-06-03$2,389,887$3,647,138$1,938,37753%
2024-09-09$2,389,887$3,647,138$1,997,27055%
2024-10-07$2,389,887$3,647,138$2,100,12058%
2024-12-09$2,389,887$3,647,138$2,272,91262%
2025-04-28$2,389,887$3,647,138$2,452,31167%
2025-05-26$2,389,887$3,647,138$2,476,04568%
2025-06-23$2,389,887$3,647,138$2,478,88568%
2025-09-08$2,389,887$3,647,138$2,554,85370%
2025-12-08$2,389,887$3,647,138$2,591,63771%
2026-04-13$2,389,887$3,647,138$2,675,94173%
2026-05-11$2,389,887$3,647,138$2,680,37573%
2026-06-22$2,389,887$3,647,138$2,683,99174%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.