The Milton Record

Sam Sherratt Trail Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

$27,282 spent so far of the $68,699 originally approved (40% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

40% of the current budget has been drawn.

Originally approved by Council$68,699
Change since approval—
Current budget$68,699
Spent to date$27,282
Against the original approval$41,417 not yet spent — still in progress

Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$68,699$68,699$6,0909%
2026-06-22$68,699$68,699$8,37612%
2026-09-14$68,699$68,699$27,28240%

The figure Council approved has not changed across these statements. Spending against it rose by $21,192 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Parks Redevelopment

Filed by the Town under Community Services / Active / Community Services / Parks / Parks Redevelopment.

Elsewhere on this site