Harwood Park Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

$46,765 spent so far of the $382,536 originally approved (15% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $61,145 to $321,391 (-16%).

15% of the current budget has been drawn.

Originally approved by Council$382,536
Change since approval-$61,145
Current budget$321,391
Spent to date$46,765
Against the original approval$335,771 not yet spent — still in progress

Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (8 statements)

Statement dateApprovedCurrent budgetSpent%
2025-05-26$53,018$49,622$2,7906%
2025-06-23$53,018$49,622$3,2877%
2025-09-08$53,018$49,622$9,96920%
2025-12-08$53,018$49,622$29,40359%
2026-04-13$53,018$49,622$38,48278%
2026-05-11$435,554$371,013$49,70313%
2026-06-22$435,554$371,013$53,91115%
2026-09-14$382,536$321,391$46,76515%

The figure Council approved changed by $329,518 between 2025-05-26 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $43,975 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Parks Redevelopment

Filed by the Town under Community Services / Active / Community Services / Parks / Parks Redevelopment.

Elsewhere on this site