Trudeau Park Redevelopment

Community Services / Active / Community Services / Parks / Parks Redevelopment

Budget

$589,167 spent so far of the $647,746 originally approved (92% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $7,922 to $639,824 (-1%).

92% of the current budget has been drawn.

Originally approved by Council$647,746
Change since approval-$7,922
Current budget$639,824
Spent to date$589,167
Against the original approval$58,579 not yet spent — still in progress

Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$718,203$709,377$630,93889%
2025-05-26$647,746$639,824$570,13089%
2025-06-23$647,746$639,824$570,96789%
2025-09-08$647,746$639,824$571,85189%
2025-12-08$647,746$639,824$588,90392%
2026-04-13$647,746$639,824$589,08592%
2026-05-11$647,746$639,824$589,08592%
2026-06-22$647,746$639,824$589,08592%
2026-09-14$647,746$639,824$589,16792%

The figure Council approved changed by $70,457 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.