Community Services / Active / Community Services / Parks / Parks Redevelopment
$7,364 spent so far of the $129,648 originally approved (8% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later reduced the budget by $34,158 to $95,490 (-26%).
8% of the current budget has been drawn.
| Originally approved by Council | $129,648 |
|---|---|
| Change since approval | -$34,158 |
| Current budget | $95,490 |
| Spent to date | $7,364 |
| Against the original approval | $122,284 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-05-26 | $53,018 | $52,716 | $2,093 | 4% |
| 2025-06-23 | $53,018 | $52,716 | $2,310 | 4% |
| 2025-09-08 | $53,018 | $52,716 | $5,792 | 11% |
| 2025-12-08 | $53,018 | $52,716 | $22,195 | 42% |
| 2026-04-13 | $53,018 | $52,716 | $30,349 | 58% |
| 2026-05-11 | $182,666 | $148,206 | $39,618 | 27% |
| 2026-06-22 | $182,666 | $148,206 | $44,834 | 30% |
| 2026-09-14 | $129,648 | $95,490 | $7,364 | 8% |
The figure Council approved changed by $76,630 between 2025-05-26 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $5,271 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Community Services / Parks / Parks Redevelopment.