Corporate Services / Pending Closure / Information Technology
Finished at $271,226 against an original approval of $277,866 — $6,640 under.
Council later reduced the budget by $6,640 to $271,226 (-2%).
100% of the current budget has been drawn.
| Originally approved by Council | $277,866 |
|---|---|
| Change since approval | -$6,640 |
| Current budget | $271,226 |
| Spent to date | $271,226 |
| Against the original approval | $6,640 under |
Source: capital financial statement, document 16410, page 5. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-09-08 | $586,847 | $297,445 | $297,445 | 100% |
| 2026-09-14 | $277,866 | $271,226 | $271,226 | 100% |
The figure Council approved changed by $308,981 between 2025-09-08 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Pending Closure / Information Technology.