Hazardous Material Equipment Replacement

Corporate Services

Budget

$12,799 spent so far of the $17,510 originally approved (73% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

73% of the current budget has been drawn.

Originally approved by Council$17,510
Change since approval
Current budget$17,510
Spent to date$12,799
Against the original approval$4,711 not yet spent — still in progress

Source: capital financial statement, document 15221, page 5. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (15 statements)
Statement dateApprovedCurrent budgetSpent%
2023-05-08$25,750$25,7500%
2023-06-19$25,750$25,7500%
2023-09-11$25,750$25,750$7503%
2023-09-11$25,750$25,750$7503%
2023-10-23$25,750$25,750$7503%
2023-12-18$25,750$25,750$7503%
2024-04-15$25,750$25,750$7,36729%
2024-05-13$41,200$41,200$7,36718%
2024-06-03$41,200$41,200$8,94522%
2024-09-09$41,200$41,200$9,39523%
2024-10-07$41,200$41,200$9,39523%
2024-12-09$41,200$41,200$28,92670%
2025-04-28$41,200$41,030$41,030100%
2026-05-11$17,510$17,510$9,17352%
2026-06-22$17,510$17,510$12,79973%

The figure Council approved changed by $8,240 between 2023-05-08 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Corporate Services

Filed by the Town under Corporate Services.

Elsewhere on this site