The Milton Record

Dry Hydrant Systems

Corporate Services

Budget

Spent $17,559 against an original approval of $15,450$2,109 over (+14%).

Council has not changed this budget since approving it.

114% of the current budget has been drawn.

Originally approved by Council$15,450
Change since approval
Current budget$15,450
Spent to date$17,559
Against the original approval$2,109 over

Source: capital financial statement, document 15221, page 5. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (13 statements)
Statement dateApprovedCurrent budgetSpent%
2024-05-13$21,548$21,548$8,54040%
2024-06-03$21,548$21,548$8,54040%
2024-09-09$21,548$21,548$9,16843%
2024-10-07$21,548$21,548$9,16843%
2024-12-09$21,548$21,548$9,16843%
2025-04-28$21,548$20,398$20,398100%
2025-05-26$15,450$15,4500%
2025-06-23$15,450$15,4500%
2025-09-08$15,450$15,450$4503%
2025-12-08$15,450$15,450$11,25973%
2026-04-13$15,450$11,259$1000%
2026-05-11$15,450$15,4500%
2026-06-22$15,450$15,450$17,559114%

The figure Council approved changed by $6,098 between 2024-05-13 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Corporate Services

Filed by the Town under Corporate Services.

Elsewhere on this site