The Milton Record

Expanded Asphalt Program

Rural Roads Redevelopment

Budget

$4,684,467 spent so far of the $12,655,652 originally approved (45% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $2,281,099 to $10,374,553 (-18%).

45% of the current budget has been drawn.

Originally approved by Council$12,655,652
Change since approval-$2,281,099
Current budget$10,374,553
Spent to date$4,684,467
Against the original approval$7,971,185 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (45 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$5,423,400$4,913,151$2,899,61859%
2022-12-19$7,237,673$5,231,627$4,869,49993%
2023-03-27$3,061,971$2,843,257$2,060,29872%
2023-03-27$4,292,662$2,954,012$2,772,65294%
2023-03-27$5,306,440$3,678,581$3,678,581100%
2023-05-08$8,138,073$7,919,359$2,104,63727%
2023-05-08$4,292,662$2,954,012$2,773,84494%
2023-06-19$8,138,073$6,754,314$2,104,88831%
2023-06-19$4,292,662$2,954,012$2,773,84494%
2023-09-11$5,380,576$4,296,817$338,5148%
2023-09-11$7,050,159$5,071,450$4,724,12893%
2023-09-11$5,380,576$4,296,817$338,5148%
2023-09-11$7,050,159$5,071,450$4,724,12893%
2023-10-23$5,380,576$4,296,817$2,618,58661%
2023-10-23$7,050,159$5,071,450$4,726,52793%
2023-12-18$5,380,576$4,296,817$2,888,22167%
2023-12-18$7,050,159$5,071,450$4,740,38393%
2024-04-15$5,076,102$3,083,031$2,771,07890%
2024-04-15$7,050,159$5,071,450$4,753,77894%
2024-04-15$304,474$223,987$223,987100%
2024-05-13$8,849,772$6,856,701$2,786,55441%
2024-05-13$7,050,159$5,071,450$4,754,80594%
2024-06-03$8,849,772$5,697,108$2,817,72349%
2024-06-03$7,050,159$5,071,450$4,754,80594%
2024-09-09$8,849,772$5,697,108$3,062,31454%
2024-09-09$4,859,202$3,627,608$3,359,63993%
2024-10-07$8,849,772$5,697,108$3,114,00855%
2024-10-07$4,859,202$3,627,608$3,359,84893%
2024-12-09$8,849,772$5,697,108$4,474,32179%
2024-12-09$4,859,202$3,627,608$3,360,26893%
2025-04-28$8,849,772$5,697,108$4,663,43582%
2025-04-28$2,757,497$2,117,438$1,967,07693%
2025-04-28$2,101,705$1,395,9691395969%
2025-05-26$12,953,340$9,800,676$4,721,54248%
2025-05-26$2,757,497$2,117,438$1,967,18293%
2025-06-23$12,953,340$9,019,542$4,729,32752%
2025-06-23$2,757,497$2,117,438$1,967,18293%
2025-09-08$12,953,340$9,107,940$4,872,26153%
2025-09-08$2,757,497$1,971,336$1,967,211100%
2025-12-08$12,953,340$9,107,940$7,113,01678%
2025-12-08$2,757,497$1,971,336$1,967,211100%
2026-04-13$7,877,238$5,700,131$4,629,26581%
2026-04-13$7,833,599$4,816,045$4,816,045100%
2026-05-11$12,655,652$10,478,545$4,681,89545%
2026-06-22$12,655,652$10,374,553$4,684,46745%

The figure Council approved changed by $7,232,252 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Rural Roads Redevelopment

Filed by the Town under Rural Roads Redevelopment.

Elsewhere on this site