The Milton Record

Appleby Line

Rural Roads Redevelopment

Budget

$965,687 spent so far of the $7,088,480 originally approved (13% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $115,364 to $7,203,844 (+2%).

13% of the current budget has been drawn.

Originally approved by Council$7,088,480
Change since approval$115,364
Current budget$7,203,844
Spent to date$965,687
Against the original approval$6,122,793 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (24 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$818,462$1,136,706$521,23446%
2023-03-27$818,462$1,136,706$620,72655%
2023-05-08$2,716,430$4,701,776$651,82414%
2023-06-19$2,716,430$4,701,776$655,65314%
2023-09-11$2,716,430$4,701,776$1,989,18142%
2023-09-11$2,716,430$4,701,776$1,989,18142%
2023-10-23$2,716,430$4,727,867$2,415,59051%
2023-12-18$2,716,430$4,727,867$3,292,65770%
2024-04-15$2,602,136$4,304,011$3,566,85383%
2024-04-15$114,294$408,207$408,207100%
2024-05-13$2,602,136$4,304,011$3,586,80883%
2024-06-03$2,602,136$4,304,011$3,590,56483%
2024-09-09$2,602,136$4,304,011$3,615,80084%
2024-10-07$2,602,136$4,304,011$3,733,27587%
2024-12-09$2,602,136$4,421,356$3,835,44487%
2025-04-28$2,602,136$4,421,356$3,917,14489%
2025-05-26$8,986,448$10,805,668$3,934,81836%
2025-06-23$8,986,448$10,805,668$3,942,56536%
2025-09-08$8,986,448$10,805,668$4,145,64738%
2025-12-08$8,986,448$10,805,668$4,214,79439%
2026-04-13$7,088,480$7,284,424$874,39912%
2026-04-13$1,897,968$3,467,154$3,467,154100%
2026-05-11$7,088,480$7,331,027$927,19413%
2026-06-22$7,088,480$7,203,844$965,68713%

The figure Council approved changed by $6,270,018 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
Appleby Line13% drawn
C350005
Proposedcollector6 months 2025+ 2 months 2026original $7,088,480budget raised $115,364

Other lines under Rural Roads Redevelopment

Filed by the Town under Rural Roads Redevelopment.