Community Services / Active / Infrastructure Management / Bridges/Culverts Growth
Spent $13,010,639 against an original approval of $12,770,017 — $240,622 over (+2%).
Council later raised the budget by $240,622 to $13,010,639 (+2%).
100% of the current budget has been drawn.
| Originally approved by Council | $12,770,017 |
|---|---|
| Change since approval | $240,622 |
| Current budget | $13,010,639 |
| Spent to date | $13,010,639 |
| Against the original approval | $240,622 over |
Source: capital financial statement, document 16410, page 10. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $12,770,017 | $12,770,017 | — | 0% |
| 2026-06-22 | $12,770,017 | $12,770,017 | — | 0% |
| 2026-09-14 | $12,770,017 | $13,010,639 | $13,010,639 | 100% |
The figure Council approved has not changed across these statements. Spending against it rose by $13,010,639 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Infrastructure Management / Bridges/Culverts Growth.