Community Services / Active / Infrastructure Management / Rural Roads Redevelopment
$1,075,343 spent so far of the $7,088,480 originally approved (15% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $115,364 to $7,203,844 (+2%).
15% of the current budget has been drawn.
| Originally approved by Council | $7,088,480 |
|---|---|
| Change since approval | $115,364 |
| Current budget | $7,203,844 |
| Spent to date | $1,075,343 |
| Against the original approval | $6,013,137 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 10. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $2,602,136 | $4,421,356 | $3,835,444 | 87% |
| 2025-05-26 | $8,986,448 | $10,805,668 | $3,934,818 | 36% |
| 2025-06-23 | $8,986,448 | $10,805,668 | $3,942,565 | 36% |
| 2025-09-08 | $8,986,448 | $10,805,668 | $4,145,647 | 38% |
| 2025-12-08 | $8,986,448 | $10,805,668 | $4,214,794 | 39% |
| 2026-04-13 | $7,088,480 | $7,284,424 | $874,399 | 12% |
| 2026-05-11 | $7,088,480 | $7,331,027 | $927,194 | 13% |
| 2026-06-22 | $7,088,480 | $7,203,844 | $965,687 | 13% |
| 2026-09-14 | $7,088,480 | $7,203,844 | $1,075,343 | 15% |
The figure Council approved changed by $4,486,344 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
Appleby Line Ph 3 - from Derry Road to south of hairpin turn; design underway with construction expected in 2026 depending on land and permits
Filed by the Town under Community Services / Active / Infrastructure Management / Rural Roads Redevelopment.