The Milton Record

Thompson Road (Louis St Laurent to Derry Rd)

Infrastructure Management / Urban Roads Growth

Budget

$275,305 spent so far of the $1,027,346 originally approved (25% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $54,574 to $1,081,920 (+5%).

25% of the current budget has been drawn.

Originally approved by Council$1,027,346
Change since approval$54,574
Current budget$1,081,920
Spent to date$275,305
Against the original approval$752,041 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (20 statements)
Statement dateApprovedCurrent budgetSpent%
2023-05-08$526,967$526,967$8160%
2023-06-19$526,967$526,967$8160%
2023-09-11$526,967$539,684$17,8383%
2023-09-11$526,967$539,684$17,8383%
2023-10-23$526,967$539,684$18,2863%
2023-12-18$526,967$539,684$23,9434%
2024-04-15$526,967$539,684$52,79310%
2024-05-13$526,967$539,684$55,94110%
2024-06-03$526,967$539,684$56,14610%
2024-09-09$526,967$539,684$57,69811%
2024-10-07$526,967$539,684$59,16511%
2024-12-09$526,967$539,684$73,42114%
2025-04-28$526,967$539,684$94,73518%
2025-05-26$1,027,346$1,072,029$97,8279%
2025-06-23$1,027,346$1,072,029$101,0859%
2025-09-08$1,027,346$1,072,029$133,96912%
2025-12-08$1,027,346$1,072,029$244,14023%
2026-04-13$1,027,346$1,081,920$265,61025%
2026-05-11$1,027,346$1,081,920$271,35325%
2026-06-22$1,027,346$1,081,920$275,30525%

The figure Council approved changed by $500,379 between 2023-05-08 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
Thompson Road25% drawn
C340020
Proposedarterial1 YEARoriginal $1,027,346budget raised $54,574

Other lines under Urban Roads Growth

Filed by the Town under Infrastructure Management / Urban Roads Growth.