C340020 · arterial · Proposed
$275,305 spent so far of the $1,027,346 originally approved (25% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $54,574 to $1,081,920 (+5%).
25% of the current budget has been drawn.
| Originally approved by Council | $1,027,346 |
|---|---|
| Change since approval | $54,574 |
| Current budget | $1,081,920 |
| Spent to date | $275,305 |
| Against the original approval | $752,041 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 8. Matched to this project by exact-core at 97% confidence, and reconciled against the totals stated in that document.
| Anticipated start | 2026-01-01 |
|---|---|
| Completion | 2026-12-31 |
| Duration | 1 YEAR |
| Status | PROPOSED |
| Project manager | DIANA BETANCOUR |
| Contact | 905-878-7252 ext 2398 |
| Responsibility | Town of Milton |