SWM Quality Master Plan

Storm Water Management Rehabilitation

Budget

$515,161 spent so far of the $602,550 originally approved (67% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $162,585 to $765,135 (+27%).

67% of the current budget has been drawn.

Originally approved by Council$602,550
Change since approval$162,585
Current budget$765,135
Spent to date$515,161
Against the original approval$87,389 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (20 statements)
Statement dateApprovedCurrent budgetSpent%
2023-05-08$602,550$602,5500%
2023-06-19$602,550$602,5500%
2023-09-11$602,550$602,550$17,5503%
2023-09-11$602,550$602,550$17,5503%
2023-10-23$602,550$602,550$17,5503%
2023-12-18$602,550$602,550$17,5503%
2024-04-15$602,550$602,550$17,5503%
2024-05-13$602,550$914,125$27,4463%
2024-06-03$602,550$914,125$27,4463%
2024-09-09$602,550$750,135$27,7714%
2024-10-07$602,550$750,135$27,7714%
2024-12-09$602,550$750,135$31,6274%
2025-04-28$602,550$765,135$139,66518%
2025-05-26$602,550$765,135$153,69920%
2025-06-23$602,550$765,135$162,97421%
2025-09-08$602,550$765,135$188,23925%
2025-12-08$602,550$765,135$426,99756%
2026-04-13$602,550$765,135$493,42464%
2026-05-11$602,550$765,135$504,30566%
2026-06-22$602,550$765,135$515,16167%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.