The Milton Record

Storm Sewer Network Program

Storm Water Management Rehabilitation

Budget

$2,151,775 spent so far of the $8,891,948 originally approved (24% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $112,263 to $9,004,211 (+1%).

24% of the current budget has been drawn.

Originally approved by Council$8,891,948
Change since approval$112,263
Current budget$9,004,211
Spent to date$2,151,775
Against the original approval$6,740,173 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (25 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$1,035,075$1,035,075$61,5456%
2023-03-27$1,035,075$963,965$121,39813%
2023-05-08$4,933,530$4,862,420$95,6002%
2023-06-19$4,933,530$4,862,420$110,5642%
2023-09-11$4,933,530$5,271,857$312,2716%
2023-09-11$4,933,530$5,271,857$312,2716%
2023-10-23$4,933,530$5,271,857$397,8158%
2023-12-18$4,933,530$5,271,857$584,64011%
2024-04-15$4,933,530$5,069,232$1,024,72620%
2024-05-13$9,672,629$9,808,331$1,046,78911%
2024-06-03$9,672,629$9,808,331$1,083,61111%
2024-09-09$9,468,935$9,675,747$1,152,87512%
2024-09-09$203,694-$121,201$82,49382493%
2024-10-07$9,468,935$9,675,747$1,175,56812%
2024-12-09$9,468,935$9,675,747$1,254,10713%
2025-04-28$9,468,935$9,675,747$1,356,23914%
2025-05-26$9,468,935$9,788,010$2,081,71421%
2025-06-23$9,468,935$9,788,010$2,085,27221%
2025-09-08$9,468,935$9,788,010$2,310,30024%
2025-12-08$9,468,935$9,788,010$2,543,83826%
2026-04-13$9,468,935$9,788,010$2,685,41627%
2026-05-11$8,891,948$9,004,211$2,147,66824%
2026-05-11$576,987$783,799$701,12789%
2026-06-22$8,891,948$9,004,211$2,151,77524%
2026-06-22$576,987$783,799$708,20090%

The figure Council approved changed by $458,088 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Storm Water Management Rehabilitation

Filed by the Town under Storm Water Management Rehabilitation.

Elsewhere on this site