The Milton Record

3/4 Ton Pick-ups Replacement

Community Services / Operations / Fleet Equipment - Replacement

Budget

Spent $186,546 against an original approval of $173,596$12,950 over (+7%).

Council later raised the budget by $88,581 to $262,177 (+51%).

71% of the current budget has been drawn.

Originally approved by Council$173,596
Change since approval$88,581
Current budget$262,177
Spent to date$186,546
Against the original approval$12,950 over

Source: capital financial statement, document 15221, page 7. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (21 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$171,186$162,662$158,93998%
2023-05-08$143,383$151,3210%
2023-06-19$143,383$151,3210%
2023-09-11$143,383$151,321$4,1763%
2023-09-11$143,383$151,321$4,1763%
2023-10-23$143,383$151,321$77,74851%
2023-12-18$143,383$151,321$77,74851%
2024-05-13$165,516$165,5160%
2024-06-03$165,516$165,5160%
2024-09-09$165,516$165,516$4,8213%
2024-10-07$165,516$165,516$4,8213%
2024-12-09$165,516$165,516$149,20090%
2025-04-28$165,516$165,516$149,20090%
2025-05-26$339,112$339,112$149,20044%
2025-06-23$339,112$339,112$149,20044%
2025-09-08$173,596$150,307$5,0563%
2025-09-08$165,516$149,200149200%
2025-12-08$173,596$150,307$186,546124%
2026-04-13$173,596$190,087$186,54698%
2026-05-11$173,596$190,087$186,54698%
2026-06-22$173,596$262,177$186,54671%

The figure Council approved changed by $2,410 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Fleet Equipment - Replacement

Filed by the Town under Community Services / Operations / Fleet Equipment - Replacement.

Elsewhere on this site