Walker Neighbourhood Park - Boyne

Community Services / Active / Community Services / Parks / Parks Growth

Budget

$2,120,423 spent so far of the $2,488,809 originally approved (88% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $72,940 to $2,415,869 (-3%).

88% of the current budget has been drawn.

Originally approved by Council$2,488,809
Change since approval-$72,940
Current budget$2,415,869
Spent to date$2,120,423
Against the original approval$368,386 not yet spent — still in progress

Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$2,674,647$2,601,707$2,262,70587%
2025-05-26$2,674,647$2,601,707$2,264,05687%
2025-06-23$2,674,647$2,601,707$2,264,61487%
2025-09-08$2,488,809$2,415,869$2,119,05488%
2025-12-08$2,488,809$2,415,869$2,120,06788%
2026-04-13$2,488,809$2,415,869$2,120,28788%
2026-05-11$2,488,809$2,415,869$2,120,28788%
2026-06-22$2,488,809$2,415,869$2,120,28788%
2026-09-14$2,488,809$2,415,869$2,120,42388%

The figure Council approved changed by $185,838 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Parks Growth

Filed by the Town under Community Services / Active / Community Services / Parks / Parks Growth.