Sauble Park - Boyne

Community Services / Active / Community Services / Parks / Parks Growth

Budget

$55,816 spent so far of the $691,728 originally approved (8% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $49,313 to $741,041 (+7%).

8% of the current budget has been drawn.

Originally approved by Council$691,728
Change since approval$49,313
Current budget$741,041
Spent to date$55,816
Against the original approval$635,912 not yet spent — still in progress

Source: capital financial statement, document 16410, page 7. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$691,728$741,041$28,0794%
2026-06-22$691,728$741,041$28,2224%
2026-09-14$691,728$741,041$55,8168%

The figure Council approved has not changed across these statements. Spending against it rose by $27,737 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.