Community Services / Active / Operations / Roadway Maintenance
$810,503 spent so far of the $2,123,691 originally approved (38% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
38% of the current budget has been drawn.
| Originally approved by Council | $2,123,691 |
|---|---|
| Change since approval | — |
| Current budget | $2,123,691 |
| Spent to date | $810,503 |
| Against the original approval | $1,313,188 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 9. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-12-08 | $2,067,311 | $2,067,311 | $1,267,319 | 61% |
| 2026-04-13 | $1,042,230 | $1,042,230 | $775,994 | 74% |
| 2026-05-11 | $2,123,691 | $2,123,691 | $775,994 | 37% |
| 2026-06-22 | $2,123,691 | $2,123,691 | $775,994 | 37% |
| 2026-09-14 | $2,123,691 | $2,123,691 | $810,503 | 38% |
The figure Council approved changed by $56,380 between 2025-12-08 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Operations / Roadway Maintenance.