The Milton Record

Ice Resurfacer

Community Services / Active / Operations / Fleet Equipment - Replacement

Budget

$7,375 spent so far of the $253,203 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $35,630 to $288,833 (+14%).

3% of the current budget has been drawn.

Originally approved by Council$253,203
Change since approval$35,630
Current budget$288,833
Spent to date$7,375
Against the original approval$245,828 not yet spent — still in progress

Source: capital financial statement, document 16410, page 8. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (11 statements)

Statement dateApprovedCurrent budgetSpent%
2022-12-19$113,300$171,393$3,3002%
2023-05-08$113,300$205,901$3,3002%
2024-12-09$366,186$458,787$210,26746%
2025-05-26$252,886$252,886$7,3663%
2025-06-23$252,886$252,886$206,96782%
2025-09-08$252,886$252,886$206,96782%
2025-12-08$252,886$252,886$206,96782%
2026-04-13$252,886$252,886$206,96782%
2026-05-11$474,478$474,478$206,96744%
2026-06-22$474,478$503,162$206,96741%
2026-09-14$253,203$288,833$7,3753%

The figure Council approved changed by $139,903 between 2022-12-19 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $4,075 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Fleet Equipment - Replacement

Filed by the Town under Community Services / Active / Operations / Fleet Equipment - Replacement.

Elsewhere on this site