Sign Truck

Community Services / Active / Operations / Fleet Equipment - Replacement

Budget

$96,011 spent so far of the $421,159 originally approved (49% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $223,298 to $197,861 (-53%).

49% of the current budget has been drawn.

Originally approved by Council$421,159
Change since approval-$223,298
Current budget$197,861
Spent to date$96,011
Against the original approval$325,148 not yet spent — still in progress

Source: capital financial statement, document 16410, page 8. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (11 statements)

Statement dateApprovedCurrent budgetSpent%
2022-12-19$329,600$357,587$9,6003%
2023-05-08$750,759$778,746$87,48511%
2024-12-09$750,759$555,785$100,08918%
2025-05-26$750,759$654,134$100,08915%
2025-06-23$750,759$654,134$100,08915%
2025-09-08$750,759$576,249$105,94718%
2025-12-08$750,759$576,249$474,39982%
2026-04-13$421,159$197,861$96,01149%
2026-05-11$421,159$197,861$96,01149%
2026-06-22$421,159$197,861$96,01149%
2026-09-14$421,159$197,861$96,01149%

The figure Council approved changed by $91,559 between 2022-12-19 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $86,411 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.