Boulevard Works

Community Services / Active / Infrastructure Management / Urban Roads Growth

Budget

Spent $963,741 against an original approval of $895,369 — $68,372 over (+8%).

Council later raised the budget by $195,609 to $1,090,978 (+22%).

88% of the current budget has been drawn.

Originally approved by Council$895,369
Change since approval$195,609
Current budget$1,090,978
Spent to date$963,741
Against the original approval$68,372 over

Source: capital financial statement, document 16410, page 9. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$895,369$1,466,519$108,4447%
2025-05-26$895,369$1,053,863$476,09445%
2025-06-23$895,369$1,053,863$520,48849%
2025-09-08$895,369$1,090,978$934,80186%
2025-12-08$895,369$1,090,978$942,04586%
2026-04-13$895,369$1,090,978$961,04588%
2026-05-11$895,369$1,090,978$962,79688%
2026-06-22$895,369$1,090,978$963,01088%
2026-09-14$895,369$1,090,978$963,74188%

The figure Council approved has not changed across these statements. Spending against it rose by $855,297 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.