6th Line (Hwy 401 to Britannia Rd)

Community Services / Active / Infrastructure Management / Urban Roads Growth

Budget

$562,931 spent so far of the $959,703 originally approved (49% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $199,062 to $1,158,765 (+21%).

49% of the current budget has been drawn.

Originally approved by Council$959,703
Change since approval$199,062
Current budget$1,158,765
Spent to date$562,931
Against the original approval$396,772 not yet spent — still in progress

Source: capital financial statement, document 16410, page 9. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (9 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$959,703$1,023,765$75,3907%
2025-05-26$959,703$1,023,765$181,57618%
2025-06-23$959,703$1,023,765$186,05918%
2025-09-08$959,703$1,023,765$226,24622%
2025-12-08$959,703$1,023,765$444,98843%
2026-04-13$959,703$1,083,765$506,60847%
2026-05-11$959,703$1,083,765$519,72048%
2026-06-22$959,703$1,083,765$522,60448%
2026-09-14$959,703$1,158,765$562,93149%

The figure Council approved has not changed across these statements. Spending against it rose by $487,541 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Urban Roads Growth

Filed by the Town under Community Services / Active / Infrastructure Management / Urban Roads Growth.

Elsewhere on this site