Kelso Road Bridge (Structure 74)

Completed Pending Warranty / Community Services / Infrastructure Management / Bridges/Culverts Redevelopment

Budget

$1,529,724 spent so far of the $2,538,372 originally approved (94% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $916,647 to $1,621,725 (-36%).

94% of the current budget has been drawn.

Originally approved by Council$2,538,372
Change since approval-$916,647
Current budget$1,621,725
Spent to date$1,529,724
Against the original approval$1,008,648 not yet spent — still in progress

Source: capital financial statement, document 15221, page 10. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (23 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$150,538$167,877$42,36025%
2023-03-27$150,538$167,877$58,38835%
2023-05-08$150,538$167,877$62,96138%
2023-06-19$150,538$167,877$74,97945%
2023-09-11$150,538$167,877$93,00055%
2023-09-11$150,538$167,877$93,00055%
2023-10-23$150,538$167,877$101,06660%
2023-12-18$150,538$167,877$109,73365%
2024-04-15$150,538$167,877$135,05780%
2024-05-13$2,688,910$2,706,249$180,8787%
2024-06-03$2,688,910$2,780,254$195,9327%
2024-09-09$2,538,372$1,926,725$108,8706%
2024-09-09$150,538$36,247$186,785186785%
2024-10-07$2,538,372$1,926,725$266,42914%
2024-12-09$2,538,372$1,926,725$1,159,12560%
2025-04-28$2,538,372$1,926,725$1,514,82479%
2025-05-26$2,538,372$1,926,725$1,523,23179%
2025-06-23$2,538,372$1,926,725$1,525,16979%
2025-09-08$2,538,372$1,726,725$1,529,58189%
2025-12-08$2,538,372$1,726,725$1,529,58189%
2026-04-13$2,538,372$1,621,725$1,529,58194%
2026-05-11$2,538,372$1,621,725$1,529,72494%
2026-06-22$2,538,372$1,621,725$1,529,72494%

The figure Council approved changed by $2,387,834 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Infrastructure Management

Filed by the Town under Completed Pending Warranty / Community Services / Infrastructure Management / Bridges/Culverts Redevelopment.